Do I Need a Fire Statement for a Planning Application in London?

Why London councils ask for fire safety information under London Plan Policy D12, the difference between D12(A) for every scheme and D12(B) for major ones, what a householder statement covers, and how it differs from the Part B drawings for building control.

Ask for your fixed fee in writing

Name and email are required. Everything else helps us price it, but is optional.

Your enquiry goes to us and nowhere else. It is never syndicated or sold. See our privacy notice.

Photo: Philafrenzy / Wikimedia Commons, CC BY-SA 4.0

Often yes, but a short one. London Plan Policy D12(A) applies to all development, and several London councils turn it into a validation requirement, so even a house extension can be returned as invalid without some fire safety information. For a householder scheme that is a statement answering six points, or an exemption statement where the council accepts one. It is not the independent fire engineer's report under D12(B), which is only for major development. We write D12(A) statements for householder and minor schemes; they are from £125.

On this page

Which fire document applies to my scheme?

There are three, and owners often confuse them.

London Plan Policy D12(A) applies to every development proposal. It asks for the "highest standards of fire safety" and lists six things a scheme should do (London Plan 2021, chapter 3). This is the one that reaches a house extension or a loft conversion.

London Plan Policy D12(B) says all major development proposals should come with a Fire Statement, an independent fire strategy by "a third party, suitably qualified assessor". A householder application is never major. If your scheme is major, appoint a fire engineer; that is not a product we sell.

The national fire statement, introduced from 1 August 2021, applies to "relevant buildings": those with two or more dwellings or educational accommodation that are 18 m or 7 storeys or more (MHCLG guidance). No house extension meets that test.

Step by step: 1. Check; 2. Plans; 3. Answer; 4. Submit1CheckRead the council's list to see whichfire document it asks for.2PlansRead the proposed plans for escape,alarms, materials and access.3AnswerWrite a response to each of the sixD12(A) points.4SubmitThe statement goes in with the planningapplication.
Step by step

What do London councils ask a householder for?

D12(A) is policy, and each council decides through its local list what it needs to see at validation. Three current lists show how far apart they are.

Lambeth says "all applications for minor developments should be accompanied by a Fire Statement that meets the requirements of Part A of Policy D12" (Lambeth local list, item 33). If you are extending in Lambeth, plan on one.

Wandsworth asks all developments for a fire safety strategy to Policy D12, and says "exemption statements will be accepted for smaller schemes where this is not applicable" (Wandsworth checklist, July 2026). A rear extension that leaves the escape route unchanged may need only that short exemption statement.

Bromley lists a London Plan fire statement for major development, new dwellings including conversions, commercial development and changes of use, and asks non-major schemes of those types to show that D12 has been considered (Bromley validation guidance). A plain house extension in Bromley is not on that list; a house split into flats is.

Read the date on your own council's list too. A local requirement only affects validity if the list was published less than two years before you apply (MHCLG guidance, paragraph 039).

Is there an official householder form?

Not one in force from the Mayor. The GLA consulted in 2022 on draft Fire Safety London Plan Guidance, and that draft has since been withdrawn and is no longer proposed for adoption. The withdrawal "does not affect the status of Policies D5 and D12" (GLA), so the policy still applies without the guidance. What matters is that the six points are answered in the format your council's list asks for.

What does a householder D12(A) statement cover?

Each of the six points, answered for the house as proposed:

  1. Outside space for fire appliances to stop and for people to gather. For most London houses that is the street and the pavement at the front.
  2. Features that reduce risk to life, such as interlinked smoke alarms and fire-resisting doors where the layout needs them.
  3. Construction that limits fire spread, including the external wall materials and any wall close to the boundary.
  4. Means of escape, which changes most with a loft conversion that adds a storey above the first floor or an open-plan ground floor that removes the hall wall.
  5. An evacuation strategy, which for a single family house is simple: everyone leaves by the protected route.
  6. Access and equipment for firefighting, appropriate to the size and use of the house.

Most answers are a few lines, but each has to be there. The statement makes no promise about the construction detail; that is checked later.

An inspector in a hard hat and high-visibility vest kneeling by a wall socket, holding a clipboard and a small torch
Hidden services are the hardest part of regularisation, so officers may ask for tests or opening up. Photo: RDNE Stock project / Pexels (Pexels License).

What happens if I leave it out?

If your council's list asks for D12 information and the application arrives without it, the council can treat the application as invalid and write to ask for it. The decision period does not start until the missing document arrives, so a two-page statement left out can cost weeks. If you believe the requirement does not apply to your scheme, the national guidance sets out the article 12 notice route for disputing it (MHCLG guidance, paragraph 049). For most householders, writing the short statement is quicker than the dispute.

How is it different from the Part B fire drawings?

The planning statement explains the approach to fire safety at planning stage. The detailed design, such as the protected stair, the fire doors, the alarm grade and the escape windows, is then shown on the building regulations drawings and checked by building control against Approved Document B Volume 1, the guidance for dwellings.

The two should say the same thing. Our fire strategy plan is the building regulations drawing for a loft or an HMO, and its cost is set out in our fire strategy cost guide. For the rest of the building control set, see what building control needs for an extension.

What if my extension is permitted development?

Then there is no planning application and no D12 statement. Building regulations still apply, including Part B. If your loft is permitted development, our loft permitted development guide explains the limits, and our post on whether your house is suitable for an extension covers the checks that decide whether you need an application at all.

Every report we prepare for an application, with its fee, is listed on the planning reports hub, and the fire statement service page sets out what ours includes.

Cost breakdown: Our fee £125 paid to us£125Our fee, £125, paid to usFrom £125 in all
Where the money goes, from our published prices.

Frequently asked questions

Does a loft conversion planning application need a fire statement in London? Where the council's list asks for D12 information, yes, and the loft is the case where means of escape matters most, because a new storey changes the route out of the house.

Who can write a D12(A) statement? The London Plan names a third-party, suitably qualified assessor for D12(B) on major schemes. For D12(A) on a householder or minor scheme it sets no such requirement; your council's list may say more.

Does a flat conversion need a fire statement? Usually. Bromley lists new dwellings including conversions, and Lambeth asks all minor applications for one. If the converted building is 18 m or 7 storeys or more, the national fire statement form applies as well.

Will the fire statement satisfy building control? No. It answers the planning policy. Building control checks the detailed design against Part B separately.

A red break-glass fire alarm call point fixed to a rough cream-coloured wall

Fixed fee, in writing

London Plan fire statement: from £125

The fee is published and confirmed in writing before any work starts. Council fees are passed through at cost, never marked up.

Get my fixed fee

Photo: Srattha Nualsate / Pexels

The figures, with their sources

London Plan fire statement: the fee, fixed

from £125

from £125

No council fee for this service. A fixed fee, confirmed in writing before any work starts.

Get my fixed fee

What you get

  • A check of your council's validation list: a full D12(A) statement, a short exemption statement, or nothing
  • Each of the six D12(A) points answered for your scheme
  • Means of escape and alarm provision described against the proposed plans
  • Materials and fire spread noted where the outside of the building changes
  • A plain note where D12(B) or the national fire statement form applies instead, so you appoint the right specialist

Ask for your fixed fee

Send the postcode and a line about the project. Photos or old plans help, and the fee comes back in writing.

Ask for your fixed fee in writing

Name and email are required. Everything else helps us price it, but is optional.

Your enquiry goes to us and nowhere else. It is never syndicated or sold. See our privacy notice.

Get a fixed quote from £125
Get my fixed fee