The drawings you need for a kitchen extension in London always include a building regulations set, and the one drawing it cannot skip is the drain. Thames Water says "it's likely that you'll need to make an application if you're building within 3 metres of a public sewer" (Thames Water, build over agreements), and a planning permission does not cover it. Planning drawings come on top only when the extension falls outside permitted development.
On this page
| Your kitchen extension | Drawings you need | What you pay us |
|---|---|---|
| Single-storey rear, within the Class A limits, on a house | Building regulations set plus beam calculations | Building regs and structural package from £1,195 |
| Side return infill in a conservation area, any extension beyond the limits, or rights removed | Planning set, then the building regulations set and calculations | Planning, building regs and structural package from £1,495 |
| Any extension to a flat | Planning set (no permitted development), then building regulations | from £1,495, plus the freeholder's consent |
A certificate of lawfulness for a permitted development extension is optional, from £795. A householder application costs £548 in council fees on top of our fee.
Does a kitchen extension need planning permission?
A kitchen extension on a London house needs no planning application if it is single-storey, at the rear and inside the Class A limits. A single-storey rear extension is permitted development up to 3m beyond the original rear wall of a terraced or semi-detached house, 4m on a detached one, and no more than 4m high (GPDO 2015, Class A).
Outside conservation areas, the larger home prior approval route stretches that to 6m and 8m, with a council fee of £249. Our prior approval service is from £625; after it, building regulations drawings are £795 and structural calculations from £425.
Three London situations take a kitchen extension out of permitted development:
- Side return infills. On a Victorian terrace with the kitchen in the narrow back addition, widening it means filling the side passage. That is a side extension beyond a side wall. In a conservation area it is never permitted development, and elsewhere it must stay single-storey, under 4m high and no wider than half the original house. Our side return guide covers it.
- Wrap-arounds. An L-shape that fills the side return and goes out the back is tested as one enlargement, against both sets of limits.
- Flats. A ground-floor flat has no householder permitted development rights, so any extension needs a planning application. Our post on extending a flat covers the freeholder's side.
Question 1 of up to 4
What type of property is it?
- Property
- Not answered yet
- Area
- Not answered yet
- Work
- Not answered yet
- Route
- Not answered yet
What planning drawings do I need for a kitchen extension in London?
The planning set for a kitchen extension shows the outside of the building and its effect on the neighbours:
- Existing and proposed ground floor plans, and a roof plan.
- Existing and proposed rear and side elevations.
- A section giving the height at the boundary, which neighbours and officers look at first.
- Location and block plans.
Our post on what a householder application needs lists each sheet. For a kitchen, the plan should already show the layout of the units, the island and the doors to the garden. Moving them later can change a rooflight or a window the council has approved.
What does building control need for a kitchen?
Building control needs everything an extension needs, which our post on what building control needs for an extension covers: foundations, walls, roof build-up, insulation and the specification. A kitchen adds five things.
1. The drain under the floor. Where a sewer shared by a terrace runs behind the houses, its manhole can sit right where the extension goes. Building within 3m of a public sewer, or within 1m of a public lateral drain, is likely to need Thames Water's agreement. A build over agreement is Thames Water's written consent to build over or near one of its public sewers. Where the sewer is 150mm or less inside and the diversion 20m or less, a minor diversion is possible instead. The survey lifts the manhole covers we can reach, and the drawings show the sewer route, the manhole and the new connections for the sink and dishwasher.
For example (illustrative, not a real job), imagine a Hackney terrace where the rear manhole sits 1.5 m from the back wall and the planned extension goes out 3 m. The sewer runs under the new floor, so the build-over application goes in with the building regulations drawings, before the builder digs the foundations.
2. Extract ventilation. Approved Document F asks for at least 30 l/s from a cooker hood that extracts to outside, or 60 l/s from another extract fan (Approved Document F, Volume 1, Table 1.1). An island hob means a ducted hood through the ceiling, so the duct route goes on the section before the joists are ordered.
3. The beam over the opening. Joining the extension to the house means taking out most of the old back wall, and sometimes the wall between the back addition and the middle room. That needs a steel beam and padstones, sized by calculation. Our post on removing a load-bearing wall explains the calculation pack. Both our packages include it, and on their own structural calculations are from £425.
4. Glazing. Bi-folds across the back and a long rooflight over the side return use glass fast. The windows, rooflights and doors in an extension should not exceed 25% of its floor area, plus the area of the openings it removes or covers. That is paragraph 10.7(d) of Approved Document L now, 10.8(d) of the 2026 edition from 24 March 2027. Over that, an energy calculation must show the extension still performs. Our Part L guide works through the sums, and the orangery drawings post runs a worked example for a glass-roofed build.
5. The escape route. If the house has a storey more than 4.5m above ground, such as a loft room on a two-storey house, Approved Document B protects the route down from it. Opening the kitchen into the hall can break that route, so the drawings show how it is kept: new partitions, or an alternative the building control body accepts. Settle it on paper before the hall wall comes down.

Full plans or building notice?
Full plans and a building notice are both lawful for a house, and one of them must be given before work starts (Building Regulations 2010, regulation 12). Where the extension is over or near a public sewer on the sewer map, requirement H4 applies and regulation 12(5) requires a full plans application, so the building notice is ruled out. A building notice has no approval stage, so questions about the drain or the beam are settled on site, with the builder waiting. Full plans gives you an approved set before work starts for the builder to price from. Near an unmapped drain, full plans is still the safer route, because Thames Water's agreement and the approved drawings then match.
Who else needs to see the drawings?
Three parties outside the council may need the drawings:
- The neighbours. Foundations within 3m of a neighbour's house that go deeper than theirs, or a wall on the boundary, bring in party wall notices. We refer those to a specialist, and our Party Wall Act guide sets out the timings.
- Thames Water, if the sewer is close.
- Your freeholder, if the property is a flat.
Work out your fee
FFP-01 · Rev AHouseholder planning fee paid to your council at submission; the building control charge is separate and set by your council or a registered building control approver.
Prices include one measured survey of a house of up to two storeys (£250). A flat or maisonette is £50 less; a house of three storeys or more is £50 more. One survey covers every service on the same job.
Plus the Planning Portal's own charge if the application goes through the Portal: up to £149 including VAT, depending on the application type, and some types have none (source).
Get this fee in writingor email hello@fixedfeeplans.co.uk
No obligation. Nothing is sent until you ask; your enquiry comes to us and nowhere else.
Frequently asked questions
Do I need building regulations for a kitchen extension under 30m²? Yes. The 30m² exemption is for conservatories and porches separated from the house. A kitchen extension joined to the house is an extension, whatever its size.
Can I move the sink without new drawings? Inside the existing house, moving a sink needs no planning drawings, but new drainage is building work and must still comply with Part H. In an extension, show it on the drainage plan, because it sets the falls and the connection to the sewer.
Does an island hob need a different extract? The rate is the same: 30 l/s with a hood ducted to outside. The duct route through the ceiling is the hard part, and it belongs on the section before the joists are ordered.
When should I apply to Thames Water? Once the drawings show the sewer route and the foundations, and before the builder starts digging. Thames Water's page sets out the application and what it needs.
If the application goes through the Planning Portal, the Portal adds its own service charge: nothing, £99 or £149 including VAT, depending on the application type and complexity, paid to the Portal at submission and not normally refunded with a council fee (Ashford Borough Council, Planning Portal service charges, 11 September 2026). It is not ours and not the council's. Other submission routes exist; where your council accepts one without a charge, we can use it.