To remove a load-bearing wall in a London house you need a structural calculation for the new beam, a plan showing the opening, and a section or detail showing how the beam bears on the walls either side. Those go to building control with a building notice or a full plans application before the wall comes out. You normally need no planning drawings at all, unless the building is listed.
On this page
Our calculations are from £425. What follows is what each piece is for, and the three London situations that add to the list.
Why building regulations and not planning?
Because the work changes the structure, not the outside. An internal knock-through on an ordinary house does not alter how it looks from the street, so it is not something a planning officer decides. It is building work, and the building regulations require it to meet Part A: loading, ground movement and disproportionate collapse (Schedule 1).
Before work starts you must give a building notice or a full plans application (regulation 12), to your council or a registered private approver. A building notice has no plan approval stage, but the officer will still ask to see the beam calculation before the opening is formed. Full plans gives you an approval in writing first, which a lender or a later buyer can rely on.
What exactly goes in the set?
For a typical knock-through between a front and back reception room, or a hall into a kitchen:
- Structural calculation. Traces the loads from roof and floors down to the opening, sizes the steel section and grade, and sizes the padstones that spread the load into the walls below. Our steel beam calculations post explains the pack in detail.
- Plan. The existing and new layout, the opening width, the beam position and which way the floor joists above run.
- Section or bearing detail. How the beam sits on its padstones, the bearing length, and the fire protection to the steel, usually plasterboard encasement.
- Notes. Temporary support while the wall is removed, and any wall below that must carry the new point loads.
Some jobs add a drawing or two. A chimney breast removed below while the stack stays above needs its own support, usually a steel or gallows brackets, and the calculation must cover it. A wall that carries the first-floor bathroom, or a back wall under an outrigger roof, can bring point loads the engineer has to follow down to the foundations, and occasionally a trial hole is needed to see what the wall stands on. If the knock-through is part of a kitchen refit, the plan should also show where new drainage and the extract run, because building control looks at those in the same visit.
What building control checks on site: the beam delivered matches the calculation, the padstones are in, the bearings are what the drawing says, and the steel is protected before it is boxed in.

Does opening up the ground floor affect fire escape?
In some London houses, yes, and it is the point owners least expect. Many terraces from Clapham to Crouch End already have a loft room. Once a house has a storey more than 4.5m above ground, Approved Document B expects a protected escape route from the top floor to the front door. Where the ground floor is open plan, new partitions are needed to enclose the stair (Approved Document B, Volume 1, paragraph 2.21).
So taking out the wall between the hall and the kitchen in a house with a loft conversion can break the route the loft relies on. The alternative in paragraph 2.23 is a package: sprinklers to the open-plan area, an REI 30 partition with an E 20 door separating the ground storey from the floors above, and the cooking area separated by REI 30 construction (Approved Document B, Volume 1). Our Part B loft guide goes through both routes. The drawings must show which one you have chosen, and it is far cheaper to decide on paper.
What if the beam bears on a party wall?
Most London terraces and semis share at least one wall with a neighbour, and a beam often bears on it. Cutting into a party wall for a padstone is work to an existing party wall, which needs notice at least two months before work starts (section 3). A neighbour who does not consent in writing within 14 days is deemed to dissent (section 5), and surveyors are then appointed.
The calculation helps here: an exact beam size and bearing position make the surveyor's job quicker. Our Party Wall Act guide explains the notices. Put the two months into your programme before booking the builder.
Is it different in a flat or a listed house?
Flats. Building regulations apply in the same way, but a London flat almost always has a lease, and structural alterations normally need the freeholder's consent under it. Many freeholders want to see the calculation and drawings before they agree. Ask early; consent often takes longer than the drawings. Walls between flats and the floors above you are not yours to alter alone.
Listed buildings. Kensington and Chelsea's guidance says the whole of a listed building is protected, inside included, and lists new openings within walls among the works that need listed building consent. It is a criminal offence to do such works without it (RBKC, Listed buildings explained). Here you do need drawings for the council, usually with a heritage statement, before building control.
How much does it cost?
Calculations are from £425. If you also need building regulations drawings for a wider project, see what building regs and structural calcs cost without planning, and for an extension at the same time, what building control needs for an extension. The structural calculations service page has the full scope. Building control's own charge is separate and paid to them.
Work out your fee
FFP-01 · Rev AChecked by building control as part of your building regulations approval.
Get this fee in writingor email hello@fixedfeeplans.co.uk
No obligation. Nothing is sent until you ask; your enquiry comes to us and nowhere else.
Frequently asked questions
How do I know if a wall is load-bearing? Clues include joists above running onto it, a wall directly above it on the next floor, or its thickness. The survey and an engineer confirm it. We do not guess, and we tell you if a site inspection is needed.
Can my builder size the beam? Building control expects calculations from a competent engineer. A builder's rule of thumb is not evidence of compliance.
Do I need full plans or is a building notice enough? Either is lawful for most houses. Full plans gives written approval before work; a building notice is quicker to give but leaves questions to be settled on site.
Can the wall come out before building control has seen the calculation? It should not. The calculation, the notice and the temporary support come first; the wall comes out last.