Yes: you need a build over agreement with Thames Water in London if your extension or its foundations come within 3 metres of a public sewer, or within 1 metre of a public lateral drain, and Thames Water is your sewerage company. That is Thames Water's own test, and it says you should not start construction before getting a build over agreement (Thames Water, Build over agreements). The next question is whether the pipe behind your house is public at all, and since 1 October 2011 a "private" shared drain may be.
On this page
- How do I know whether a public sewer runs under my garden?
- Why might a "private" drain now belong to Thames Water?
- What does a Thames Water build over agreement cost?
- How does a sewer change building control?
- What does Approved Document H say about building over a sewer?
- What do the drawings need to show?
- What if the builder has already started?
- Does a build over agreement replace planning permission?
- Frequently asked questions
| Your situation | Build over agreement? | Building control route |
|---|---|---|
| New work within 3 m of a public sewer | Apply to Thames Water | Full plans (H4 applies if the sewer is mapped) |
| New work within 1 m of a public lateral drain | Apply to Thames Water | Full plans if the drain is on the sewer map |
| Over a drain serving only your house, inside your boundary | No Thames Water agreement | Drain still protected or rerouted under Part H |
| More than 3 m from any public sewer | No | Building notice or full plans |
Fees, the 2011 transfer and what the drawings must show follow below.
How do I know whether a public sewer runs under my garden?
A sewer map or a drainage survey tells you whether a public sewer runs under your garden; looking at the garden does not. A manhole cover at the back of the house shows a pipe is there, not who owns it or how big it is. Thames Water lists three ways to find out:
- View its sewer maps free of charge by appointment, booked by email (the address is on the Thames Water page above).
- Buy a sewer map from a utility search company or through a property search. If you bought the house recently, your solicitor's drainage and water search may already include one.
- Have your builder or a drainage specialist survey the pipes inside your boundary for position and size.
A map shows the public network as Thames Water records it. A drainage survey with a camera down the pipe shows what is really there and how deep it runs. The two can disagree on an old street, so for a rear extension that sits close to a manhole it is worth having both.
Why might a "private" drain now belong to Thames Water?
A shared drain your deeds call private may have become Thames Water's public sewer in 2011. Under regulation 3 of the Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011, private sewers and lateral drains that communicated with a public sewer immediately before 1 July 2011 vested in the sewerage company, with 1 October 2011 as the vesting date. Exempt sewers and those already declared were left out.
Consider a terrace built in 1900 (an illustration, not a real job). One pipe runs behind five gardens and joins the street sewer, and the deeds call it a private drain. Because it served more than one house and connected to the public sewer before July 2011, it fits the description of a sewer that transferred. A pipe that serves only your house and stays inside your boundary is still yours. Building over it needs no Thames Water agreement, but building control will still want it protected or rerouted under Part H of the Building Regulations.

What does a Thames Water build over agreement cost?
A Thames Water build over application costs £130, £490 or £585 depending on the sewer's internal diameter, with legal costs from £1,000 on top for the largest class. Thames Water says these charges are updated on 1 April each year:
| Sewer internal diameter | Class | Application fee |
|---|---|---|
| 175mm or less | Class 1 | £130 |
| 176mm to 350mm | Class 2 | £490 |
| Over 350mm | Class 3 | £585 plus legal costs from £1,000 |
Measure the pipe before you pick a class: the diameter, not the type of house, sets the fee. Where the better answer is to move a short length of small pipe out of the way, Thames Water has a minor diversion route for sewers of 150mm or less over no more than 20 metres. It needs a refundable £2,000 cash deposit and a CCTV survey before and after the work.
These sums are paid to Thames Water and sit outside our drawing fee. The application form itself is yours to submit; our drawings give it the plans and sections it asks for.
How does a sewer change building control?
A mapped sewer under the new floor removes the building notice route. Requirement H4 of the Building Regulations says an extension must be built in a way that is not detrimental to the building or to the continued maintenance of the drain or sewer. It applies to work over a sewer shown on a map of sewers kept under section 199 of the Water Industry Act 1991 (Building Regulations 2010, Schedule 1, Part H). Regulation 12 then says work to which H4 applies needs full plans (regulation 12). The plan check has to finish before the builder can rely on the drawings.
That is why we ask about drains before drawing, not after. Our guide to urgent building regulations drawings sets out how this changes the start date.
What does Approved Document H say about building over a sewer?
Approved Document H (2015 edition), the government guidance on meeting requirement H4, sets the design limits building control checks against. Its H4 guidance applies to building over or within 3m of the centreline of a drain or sewer shown on the sewer records (GOV.UK, Approved Document H). The numbers that shape a London rear extension:
| AD H paragraph | Guidance |
|---|---|
| H4 1.3 | Do not build over a manhole or inspection chamber on a sewer serving more than one property, unless the sewer owner accepts a new access point on the line of the sewer |
| H4 1.4 | Keep a diversion route clear, not within 3m of the building |
| H4 1.5 | No more than 6m of sewer under the building without the owner's permission |
| H4 1.6 | Not over or within 3m of a sewer more than 3m deep or over 225mm diameter without the owner's permission |
| H4 1.9 | At least 100mm of granular or flexible fill round a pipe under the building |
| H4 1.12 | Sewer more than 2m deep to invert under the foundations: design the foundation as a lintel spanning at least 1.5m either side of the pipe |
Paragraph 1.3 matters for a side return infill, because a shared manhole behind the kitchen sits where the new floor wants to go.
What do the drawings need to show?
The drawings show the pipe, the foundation and the access, measured rather than guessed. Thames Water's online application has its own checklist, and that list is what you upload against. Both Thames Water and building control want to know the same thing: can the pipe still be reached, and will the new structure damage it? The drawings that answer it show:
- The sewer's line, depth and diameter, and any manhole, taken from the survey rather than copied from the map.
- The foundation in plan and section, with its distance from the pipe and its depth against the pipe's invert.
- Any lintel or bridging where a wall crosses the pipe, so no load sits on it.
- What happens to the manhole: left outside the new floor, or replaced with access the owner accepts.
Our building regulations drawings are £545 drawings + £250 survey (£795 total), with the measured survey and the submission included, and they show the drainage once its position is known. A lintel foundation over a deep sewer needs an engineer's calculations, priced separately as structural calculations from £425. Where the extension is permitted development and needs no planning application, our building regulations and structural package from £1,195 covers both. See what building control needs for an extension for the full sheet list.
What if the builder has already started?
If the builder has already started near a public sewer without an agreement, stop and find the pipe. Thames Water says you should not start construction before getting an agreement. Without one, you may not be granted a Building Regulations completion certificate, which can cause problems when you sell. Thames Water could also seek an injunction to remove the building and recover damages. Apply before the foundations go any further. If the extension is already finished, the building control side becomes a regularisation application to the council, which our sister practice handles; see our regularisation page.
Does a build over agreement replace planning permission?
A build over agreement does not replace planning permission, because it says nothing about planning, and planning permission says nothing about the sewer. Our post on what drawings builders need to price an extension puts the sewer alongside party wall work and access as items a builder must know before quoting. Each London borough page, such as Lambeth, sets out the planning side for that council.
Work out your fee
FFP-01 · Rev AThe building control charge is set by your council or a registered building control approver.
Prices include one measured survey of a house of up to two storeys (£250). A flat or maisonette is £50 less; a house of three storeys or more is £50 more. One survey covers every service on the same job.
Get this fee in writingor email hello@fixedfeeplans.co.uk
No obligation. Nothing is sent until you ask; your enquiry comes to us and nowhere else.
Frequently asked questions
Do I need a build over agreement for a conservatory or a garden room? The test is the distance to a public sewer, not the type of building. A garden room within 3 metres of a public sewer falls inside Thames Water's test like any other structure, even where it needs no planning permission for the garden room.
Can my neighbour's drain stop my extension? Not by itself. If the shared pipe is now a public sewer, Thames Water decides whether you can build over it, and the agreement, a diversion or a design that avoids it are the routes.
Is the manhole allowed inside my new kitchen? Not on a sewer serving more than one property, unless Thames Water accepts a new access point on the line of the sewer (Approved Document H, H4 paragraph 1.3). A manhole on a drain serving only your house is a building control detail, and the drawings show how access is kept.
How long does Thames Water take to decide? Thames Water's build over page does not publish a decision time, so build the application into the programme before the builder's start date rather than after.
Do I still need one if my council is not in London? The rule follows the sewerage company, not the council. Outside London, check which company runs your sewers and read its own build over rules.